Hi everyone,

Work has started with the emptying of the room and taking care of the walls and floor.

We decided not to re-do the windows for now.

amazing acoustic panels have been ordered and should arrive in 2 weeks after the walls and floor.

soundproofing the ceiling is still being planed.

After these expenses are counted we will determine what kinds of other improvements we need to do and if we reached the amount we applied for in this first proposal.

Thank you!