Hi team,
Project member: JulianaM
Target: jmm.near
Working hours: 32
Requested N: 224 N
deducting 70 N for council work (as planting air is part of the integration nearxarroz project)
Total requested = 154 N
Working report:
- Admin work in the last week of Jo residency (till the 14th of July)
- Guidance and support - Dj Riky’s residency
- Meetings with Dj Riky + Jo about ongoing projects
- Collecting materials and content to write Residency Reports in Arroz Blog
- Writing reports
- Contacting people for the next editions
- Ideating Planting AIR next steps
- Ideating the Planting AIR DAO